PPC Group (Public Power Corporation) has announced its financial results for the first nine months of 2026. Adjusted EBITDA for the nine-month period reached €1.8 billion, up 9% year-on-year, while adjusted net profit after minority interests rose to €0.5 billion, a 35% increase. This performance reflects the strength of the Group’s vertically integrated business model and the growing contribution of international operations and new investments. Total Group investments reached €2.6 billion as of September 30, 2026, up 34% compared to the same period in 2025. Of this total, 87% was directed toward renewable energy sources (RES), flexible generation, and distribution networks, as the execution of the investment plan accelerated in Q3 and is expected to intensify further in Q4.
PPC Group: Energy storage projects in Greece
Installed RES capacity reached 7.6 GW at the end of the nine-month period 2026, up 1.3 GW year-on-year, representing 59% of the Group’s total installed capacity. During the first nine months of 2026, approximately 450 MW of RES and storage capacity was added, of which 326 MW came online in Q3 alone. Additions included energy storage projects in Greece, a photovoltaic project in Italy, and operational RES portfolios in Poland, Bulgaria, and Romania.
In Poland, the Group acquired a portfolio of operational wind and solar projects totaling 175.4 MW, as well as projects of approximately 1.2 GW at various stages of development, along with a local team. These transactions establish an operational footprint and organic growth potential in this new market.
Development continued after the reporting period, with the addition of 131.7 MW of total capacity. Specifically, the acquisition of 81.9 MW of solar projects in Hungary was completed, accompanied by a local team and a project pipeline of approximately 1 GW, while a 49.8 MW storage project was added in Romania.
Taking into account both the post-period solar additions and the above agreements, pro forma installed RES capacity reached 7.9 GW in November 2026. Additionally, projects totaling 7.4 GW are under construction, ready to build, or in a competitive tendering process. Combined with installed capacity and signed agreements, the mature portfolio already covers approximately 81% of the 18.8 GW target for 2030.
Financial performance and balance sheet position
Adjusted earnings before interest, taxes, depreciation and amortization (EBITDA) increased to €1.8 billion from €1.7 billion, while adjusted net profit after minority interests rose to €0.5 billion from €0.4 billion.
Net debt stood at €4.2 billion as of September 30, 2026, with a Net Debt/EBITDA ratio of 1.9x. This level remains well below the 3.5x threshold set by the Group’s financial policy, maintaining substantial headroom for the ongoing execution of the investment plan.
Binding MoU with AWS for a data center in Western Macedonia
In September 2026, PPC Group signed a binding Memorandum of Understanding (MoU) with Amazon Web Services (AWS), establishing the framework and key terms for the development of a data center in Agios Dimitrios, Kozani, with an initial power supply capacity of 300 MW. Under the envisaged structure, PPC will provide the land, develop the buildings and supporting energy infrastructure, and supply the facility with renewable energy through long-term Power Purchase Agreements (PPAs), while AWS — upon completion of construction — will lease the data center for 15 years and install and operate the IT infrastructure. The project has the potential to scale up to 1 GW, subject to mutual agreement, market conditions, and the execution of further definitive agreements. Both companies are working toward finalizing the agreements, in parallel with completing due diligence, securing grid connection, and obtaining the required regulatory approvals. The project represents a major step in transforming Western Macedonia into an energy and technology hub.
Outlook for 2026
Based on the nine-month performance, the Group confirms its full-year 2026 targets of adjusted EBITDA of €2.4 billion, adjusted net profit after minority interests of €0.7 billion, and a dividend of €0.80 per share. Commenting on the results, Georgios Stassis, Chairman and CEO of PPC Group, stated: “The execution of our new Strategic Plan 2026–2030 is in full swing. In the nine-month period, investments increased by 34% to €2.6 billion, with a clear priority on renewables, flexible generation, and distribution networks.
Progress is already visible in our portfolio. Year-to-date, we have added approximately 0.6 GW of RES and storage projects and established an operational presence in Poland and Hungary. The local teams and significant development pipelines in both markets lay the foundation for further expanding our footprint in the years ahead.
At the same time, adjusted EBITDA reached €1.8 billion and adjusted net profit reached €0.5 billion. Based on our nine-month performance, we confirm our 2026 targets. With a Net Debt/EBITDA ratio of 1.9x, we have the financial flexibility to continue executing our plan. In Q4, we are focused on completing the projects and agreements already underway.”
Further analysis by business segment
Supply
Electricity demand in Greece remained essentially stable in the nine-month period, with a marginal decline of 0.5% compared to the same period in 2025, primarily due to more favorable weather conditions in Q3 2026. In Romania, demand fell by 2.4%, mainly reflecting milder weather and weaker economic activity.
In Greece, PPC’s average retail electricity market share stood at 50% (down from 51% in the nine-month period of 2025). On the Interconnected System, market share remained at 49% in September 2026 (unchanged from September 2025). By voltage category, market share was 10% in High Voltage (down from 13%), 32% in Medium Voltage (down from 34%), and 64% in Low Voltage (up from 63%).
In Romania, PPC’s average share of electricity sales reached 14%, down from 16% in the same period of 2025, reflecting an increasingly competitive retail environment.
Generation
Total Group electricity generation increased by 1.6 TWh to 16.9 TWh in the nine-month period of 2026, of which 2.0 TWh came from international operations.
RES generation rose by 63% to 8.3 TWh, up from 5.1 TWh, accounting for 49% of total Group generation, compared to 33% in the nine-month period of 2025. Specifically, output from large hydropower units increased by 102%, wind generation by 13%, and solar photovoltaic generation by 54%. New capacity additions and favorable wind conditions in Greece supported this growth, despite lower solar irradiation levels in Greece and Romania.
The higher RES output reduced reliance on thermal units. Natural gas generation declined to 4.7 TWh from 5.4 TWh, and oil-fired generation fell to 1.9 TWh from 2.9 TWh, primarily due to the electricity interconnection of Crete with mainland Greece. Lignite generation stood at 2.1 TWh.
As a result of the shift in the energy mix, CO₂ emissions from electricity generation fell by 17% to 6.0 million tonnes, and emission intensity declined by 25% to 0.36 tonnes CO₂/MWh from 0.47 tonnes CO₂/MWh in the nine-month period of 2025.
The Group’s position in generation markets remained broadly stable. In Greece, the average electricity generation market share stood at 30%, while in Romania the average RES generation market share was maintained at 21%.
Distribution
Investments in distribution networks in Greece and Romania reached €0.9 billion in the nine-month period, with a focus on grid resilience, digitalization, and capacity expansion.
In Greece, the SAIDI index rose to 89 minutes from 82 minutes and SAIFI to 1.33 interruptions from 1.24, impacted by outages in Western Greece caused by severe weather events in Q1. In Romania, SAIDI improved to 54 minutes from 56 minutes and SAIFI to 1.42 interruptions from 1.45.
Progress continued on smart meter deployment. Penetration increased to 27% in Greece (up from 18%) and to 65% in Romania (up from 60%), enhancing the digital capabilities of the networks and enabling more efficient grid management.
Telecommunications
The FTTH network footprint of PPC FiberGrid expanded by approximately 60% year-on-year, reaching 2.3 million homes and businesses. More than 1.5 million are already service-ready, with the target remaining to cover over 3.8 million by end of 2028.
Following the non-binding term sheet signed in June, PPC and Vodafone Greece continue working toward finalizing an agreement on the combination of PPC FiberGrid and Fiber2All operations.
Electric mobility
PPC continues to expand the largest public charging network in Greece while broadening its presence in Romania. At the end of the nine-month period 2026, the combined network across both countries comprised 4,967 charging points, representing a 32% increase year-on-year.